ECONOMICS IN CONTRACT LETTING | 351 |
and the employees' bonus would be:
$203,200 - $162,560 = $40,640.
which is exactly 25% of $162,560.
In respect to the division of this last amount between the contractor
and the owner, its ratio to total cost is:
$162,560 ÷ $1,100,000 = 0.148, or 14.8%.
From the diagram for profit division (Fig. 33a) we find the division of this percentage to be:
Contractor......................... 8.9%
Owner.............................. 5.9%
This makes the total payment by the owner to the contractor:
$1,100,00O X 108.9 = $1,197,900.
Let us now take a case where there is a diminution in the estimated
quantities of materials. Using the same case as before in respect to
estimated quantities and tender, we shall assume the following actual
quantities of materials:
|
Earthwork | 1,050,000 cu. yds.
| Loose rock | 50,000 " |
Solid rock | 20,000 " |
Concrete | 8,000 " |
Wooden trestle | 1,800 lin. ft. |
Steel work | 450,000 lb. |
The cost of the unclassified work was $20,000, as in the preceding case.
The revised estimate is, therefore, as follows:
|
Earthwork | 1,050,000 cu. yds. @ $0.625= $656,250 |
Loose rock | 50,000 " @ 1.25 = 62,500 |
Solid rock | 20,000 " @ 1.875 = 37,500 |
Concrete | 8,000 " @ 25.00 = 200,000 |
Wooden trestle | 1,800 lin. ft. @ 62.50 = 112,500 |
Steelwork | 450,000 lb. @ 0.10 = 45,000 |
Unclassified work | $20,000 X 1.3 = 26,000 |
|
|
Summation, or "Sum D" | = $1,139,750 |
The difference between "Sum D" and "Sum C" equals
$1,139,750 - $1,250, 000 = - $110,250.
![](EP351.gif)
|
|