TITLE ABOUT CONTENTS INDEX GLOSSARY < PREV NEXT >
 
 
ECONOMICS IN CONTRACT LETTING351

and the employees' bonus would be:

$203,200 - $162,560 = $40,640.

which is exactly 25% of $162,560.

In respect to the division of this last amount between the contractor and the owner, its ratio to total cost is:

$162,560 ÷ $1,100,000 = 0.148, or 14.8%.

From the diagram for profit division (Fig. 33a) we find the division of this percentage to be:

Contractor......................... 8.9%

Owner.............................. 5.9%

This makes the total payment by the owner to the contractor:

$1,100,00O X 108.9 = $1,197,900.

Let us now take a case where there is a diminution in the estimated quantities of materials. Using the same case as before in respect to estimated quantities and tender, we shall assume the following actual quantities of materials:

Earthwork1,050,000 cu. yds.
Loose rock50,000      "      
Solid rock20,000      "      
Concrete8,000      "      
Wooden trestle1,800 lin. ft.    
Steel work450,000 lb.        

The cost of the unclassified work was $20,000, as in the preceding case.

The revised estimate is, therefore, as follows:

Earthwork1,050,000 cu. yds. @ $0.625= $656,250
Loose rock50,000         "     @   1.25     = 62,500
Solid rock20,000       "       @   1.875   = 37,500
Concrete8,000         "      @ 25.00   = 200,000
Wooden trestle1,800 lin. ft.       @ 62.50   = 112,500
Steelwork450,000     lb.       @   0.10     = 45,000
Unclassified work$20,000 X 1.3 = 26,000

     Summation, or "Sum D"= $1,139,750

The difference between "Sum D" and "Sum C" equals

$1,139,750 - $1,250, 000 = - $110,250.

 

 

 
TITLE ABOUT CONTENTS INDEX GLOSSARY < PREV NEXT >
 
Lichtenberger Engineering Library - The University of Iowa Libraries
Contact Us
© 2003 The University of Iowa