TITLE ABOUT CONTENTS INDEX GLOSSARY < PREV NEXT >
 
 
350 ECONOMICS OF BRIDGEWORK Chapter XXXIII
 

 

  Schedule B.
Earthwork $0.50 X 1.25 = $0.625
Loose rock 1.00 X 1.25 = 1.25
Solid rock 1.50 X 1.25 = 1.875
Concrete 20.00 X 1.25 = 25.00
Wooden trestle 50.00 X 1.25 = 62.50
Steelwork 0.08 X 1.25 = 0.10

The actual quantities of the materials in the completed job were, as follows:

Earthwork 980,000 cu. yds.
Loose rock 110,000       "    
Solid rock 50,000      "    
Concrete 10,500      "    
Wooden trestle 2,100 lin. ft.  
Steelwork 480,000 lbs.     

In addition, there was done by the contractor certain "unclassified work" which actually cost him for labor and materials $20,000.

The revised estimate is, therefore, as follows:

Earthwork980,000 cu. yds. @ $0.625 = $612,500
Loose rock110,000  "     @   1.25     = 137,500
Solid rock50,000    "    @   1.875     = 93,750
Concrete10,500    "     @ 25.00    = 262,500
Wooden trestle:2,100 lin. ft.   @   62.50 = 131,250
Steelwork480,000   lbs.     @   0. 10   = 48,000
Unclassified work$20,000 X 1.3 = 26,000
 
     Summation, or "Sum D" = $1,311,500

The difference between "Sum D" and "Sum C" equals

$1,311,500- $1,250,000 = $61,500.

 

For this ratio, the diagram, Fig. 33b, gives a corrective ratio of 0.865, which multiplied by $61,500 gives $53,198, say, $53,200, making the corrected limit, or "Sum E," = $1,250,000 + $53,200 = $1,303,200.

If the total actual cost of the work, including that of the unclassified work without allowance for superintendence or overhead, amounted to $1,100,000, the total profit would be:

$1,303,200 - $1,100,000 = $203,200.

Of this, the joint share of the contractor and the owner would be:

$203,200 ÷ 1.25 = $162,560;

 

 
TITLE ABOUT CONTENTS INDEX GLOSSARY < PREV NEXT >
 
Lichtenberger Engineering Library - The University of Iowa Libraries
Contact Us
© 2003 The University of Iowa