material on the outside, or else to employ a double-wall cofferdam filled with clay.
In relation to the comparative economics of a caisson, put down by
open-dredging to a depth that is absolutely great enough to insure against
disaster from scour, and a crib sunk to a reasonable depth and filled with
long piles, the latter generally will be found to be much less expensive; but
cases will occasionally occur when the reverse is true, hence it is well always
to make complete comparative estimates of cost. These require only a
few minutes' work for an experienced bridge computer.
Once in a while it occurs that the pneumatic process has to be employed
for one or more piers of a long bridge, the others being sunk by open-
dredging. The question then arises as to how many to put down by the
more expensive process; and it should be solved more with reference to the
expediting of the construction than to using pneumatics only where actually required. For instance, if all the piers but one could be handled by
open-dredging, it would be found that the unit price for the base of that one
would run extravagantly high, because it would have to take care of a
large overhead charge for use and transportation both to and fro of the
pneumatic machinery and other outfit. In that case one should figure how
much it would actually cost to put down another pier by pneumatics
when everything necessary is on the ground and ready to move over to
the site of the next pier, then compare the result with the cost of that pier
sunk by open-dredging. Generally but little difference will be found,
and, therefore, it might prove truly economic to keep both outfits occupied.
The sooner any piece of bridge construction is finished, the sooner will
the erection contractor be ready to undertake another contract—besides
it is often the case that an expeditious handling of the work will avoid a
rise of river or the advent of other unfavorable working conditions. It is,
therefore, logical to conclude as a general proposition that the harder a
contractor drives his work the more money will he net from his operations,
even if it appear to the casual observer that lie is spending cash rather
recklessly for the purpose of finishing the work quickly. Of course, if the
contractor is absolutely sure that he will have no work at all to keep his
force occupied after a certain job that he is on is completed, it will not pay
him to spend any extra money to rush it; but, on the other hand, there is
nothing to be gained by dragging it out unnecessarily. It would be better
to finish it and trust to luck about getting another contract.
In foundations for trestles there sometimes arises the economic question
whether, in order to obtain the requisite bearing area, it would be better
to use plain concrete and go rather deep by stepping off the base in the old-
fashioned way, or to spread out quickly by adopting reinforcement. The
surest way to settle the question is to proportion a pedestal or two by each
method and compare results. If for any reason the cost of the excavation
should run high, the reinforcement method will have a decided advantage.
Again, as the volume of the concrete is much smaller for that type of base
|