The original cost of water-proofing is a function of a number of different
factors. The cost of the material itself delivered at site, that of the direct
labor involved in placing it, the cost of such provisions as are made for
flashing along the lines of termination of the water-proofing, the cost of
the protective or armor coat, the additional depth of flooring and the
greater strength that must be provided in steel bridges to carry the dead
load of the water-proofing and its protection, and the accessibility of the
site of the work, are all considerations that influence the solution of this
question of economics. It is readily seen that the cost of water-proofing
must be a fundamentally variable factor, as well as one which fluctuates
with the building-material market. Moreover, the cost per square foot is
usually greater in the case of steel bridges than when the protection is
applied to concrete viaducts; because, in the latter, the increase in the
dead load does not materially affect the design, and also because in concrete bridges the protection coat is usually a part of the paving-floor system
(except in bridges of the solid-spandrel, earth-filled type), and hence
involves no additional cost. At present-day prices, however, a cost of 40
cents per square foot for water-proofing steel bridges or 35 cents per square
foot for water-proofing concrete bridges is a fair average.
The relative cost, i.e., the cost of the water-proofing as compared with
the total cost of the structure, is also variable. In the case of unique steel
bridges, such as the Hell Gate Arch or the Quebec Cantilever Bridge over
the St. Lawrence River, or in unusual concrete bridges, such as the Tunkhannock Creek Viaduct on the D. L. & W. R. R., this percentage cost is
abnormally low, because of the extremely high cost of those structures per
square foot of floor area. But such structures as those are so unusual that
we may ignore them in our cost considerations, and base our results on the
more common types of bridges.
Data gathered from several eastern railroads show that, of the total cost of a steel bridge, four per cent is properly chargeable to water-proofing. In computing this figure various standard types of bridges were considered i.e., concrete-filled trough-floors, plate-girders with transverse I-beam floors, longitudinal I-beam floors with steel-plate, and deck-girder bridges. Cost
data were also gathered for different periods-before, during, and after the
war-and the results were averaged. It might be remarked in passing that
the advance in water-proofing costs has not kept pace with the advance in
other elements of construction. For example, in 1914 the steel in a certain
bridge cost $73 per ton erected and the water-proofing 28 cents per square foot.
In 1917-1918 the steel in a bridge of exactly the same type cost $143
per ton erected, while the water-proofing cost but 35 1/2 cents per square foot.
Thus, although the steel increased in cost ninety-six per cent, the water-proofing increased only twenty-seven per cent. When it is stated, therefore, that the cost of water-proofing averages four per cent of the cost of the structure, we are taking a figure which is really extreme and which we may safely assume will not be exceeded, except in isolated and very
|