force it so as to make it carry satisfactorily heavier loads than those for which it was proportioned. In fact, the character of detailing employed previous to the nineties, in which decade the science of bridge design began
to be established, was so outrageously unscientific as to lead the author to
suggest the axiom that "the best way to repair an old bridge is to throw it
into the scrap heap and build a new one."
Quite often bridges are repaired, which, from the standpoint of true
economy, should be relegated to the discard. One such case of some
importance occurred in the author's practice in the late eighties. It was an
old Post Truss bridge across the Missouri River at Fort Leavenworth,
Kansas, which had been seriously injured by the burning of a large portion
of the wooden floor. The total cost of the repairs was somewhat in excess
of one hundred thousand dollars—an amount greater than the sum total of
all the subsequent incomes from both railway and highway traffic. In
extenuation of his action in repairing this structure, the author might
mention the fact that he was not consulted about the economics of the
case or the advisability of repairing, but was simply given the job of engineering the reconstruction of the damaged structure. However, he is not
sure that, at that stage of his career and in those days of primitive bridge
design and construction, his judgment was far enough developed to enable
him to come to a truly economic decision, had the problem of the economics
of the case been submitted to him.
The method of solving such a problem is to estimate upon a liberal basis
the probable cost of the repairs, and upon a conservative basis the probable
duration of life of the repaired structure, also the probable costs of an entirely
new bridge both at the date of consideration and at the expiration of the
said life. If the latter cost, plus the cost of the repairs with compound
interest thereon up to the time of the renewal, plus the net cost of removal of
old structure (i.e., cost of the work less scrap value) is smaller than the net cost of immediate removal, plus the cost of a new structure, built immediately, plus compound interest on the sum of these two costs at the
assumed later date, plus the small value of the deterioration of the new
structure in the interval between the said two dates, then the repairs will
be warranted.
It is evident that the correct determination of the answer to any such
economic question demands wide experience, sound judgment, correct
vision, and a practical acquaintance with the theory of economics.
In the old days a large portion of the work of bridge examination and
repairing fell to the lot of the consulting engineers; but such now is far
from being the case, because it is only for very large and important structures, or those having movable spans of a complicated character, that the
independent specialists are retained on repairs and reconstruction. Such
work is ordinarily done by the bridge engineers regularly employed by the
railroads, the states, and the municipalities; and these men have become
exceedingly expert therein.
|