156 |
ECONOMICS OF BRIDGEWORK |
Chapter XVIII |
occur. In the case of long piles driven into soft material, it is almost entirely the side friction which gives them supporting power. Again, someone may question the correctness of loading sand apparently as high
as nine tons per square foot at a depth of 250 feet below low water level,
when the depth of water is eighty feet; but it must be remembered that the
net weight of 170 feet of earth loads the soil some five tons per square foot,
and that before any settlement can occur, the material adjacent to the
caisson has to be raised. The reason for this is that the sand at such a
great depth is practically incompressible, so that for any settlement to
occur it must flow. It cannot flow downward or laterally, because there is
no vacant space for it to fill; consequently, if flow it must, it will have to
pass upward; and, in order to do so, it must lift a large column of the adjacent solid material. In the author's opinion, it would take an excessively
large unit loading on the base of a filled caisson resting on coarse sand at a
depth of two hundred and fifty feet to cause the slightest settlement.
|
TABLE 18a
Character of structure | Weight per Lineal Foot for Flooring Exclusive of all Steel but Reinforcing Bars |
Low level, combined bridges | 5,800 pounds |
High level, combined bridges | 6,900 pounds |
Double-track-railway bridges | 900 pounds |
Single-track-railway bridges | 450 pounds |
Standard highway bridges | 6,100 pounds |
The permissible loading for long piles has been taken at forty tons per pile, this being in accordance with the author's practice for a quarter of a century; and he has never yet found any settlement to occur under such loading.
Unit Prices of Materials in Place
The following table gives the unit prices for materials in place assumed
for the purpose of this investigation:
Table 18b
|
Materials |
Condition of Market |
Low | Medium | High |
Structural steel, per pound |
4¢ |
6¢ |
8¢ |
Concrete shafts of 20' average thickness, per cubic yard |
$9.00 |
$12.00 |
$15.00 |
Mass of caissons, including all materials, for a
width of 30' and a height of 150', sunk by
open-dredging, per cubic yard |
15.00 |
20.00 |
25.00 |
Mass of cribs, including enclosed pile-heads,
per cubic yard |
15.00 |
20.00 |
25.00 |
Portion of long piles projecting below base of
crib, per lineal foot |
.75 |
1.00 |
1.25 |
|