Federal Government to undertake the said tests through the Bureau of Standards.
The matter of allowing higher intensities of working stresses for old
bridges in service than those specified for the designing of new structures
is treated at length in Chapter XLI on "Economics of Maintenance and
Repairs."
There is an economic question concerning loads to which but little
attention has hitherto been paid, viz., the best way to compute the total
loading for a foundation pile. Most engineers ignore impact altogether in
estimating the load on piles supporting piers of bridges and trestles, and the
author has often done so; but there are cases in which such practice might
be unsafe. An instance of this kind occurred in a competitive study made
by the author in relation to the rebuilding of the Galveston Causeway
after a large portion of it had been destroyed during a hurricane accompanied by a tidal wave. There the piles were comparatively short; and
they passed through a thick layer of very soft material before reaching a
somewhat firmer one. The layout under consideration was one of reinforced-concrete girders; hence the spans had to be short and the piers small.
Under such conditions the vibration from passing trains certainly would
have reached the piles from the spans with comparatively little diminution
in effectiveness; hence it was essential to allow for impact on the said
piles. They had to be proportioned also for effect of thrust of braked
trains; but, as the thrust would have been exerted when the train speed
was slowing down, it would not have been logical to combine the thrust-effect with the full value of impact. That was an instance where the consulting engineer's judgment had to be relied upon to determine the proper
combination of loads, and where a familiarity with the principles of true
economics would be of great value to the owners.
The reason why the impact on foundation piles may either be assumed
comparatively small, or possibly ignored altogether, are as follows:
First. If allowed for at all, the impact should be assumed for a span-length equal to the sum of the lengths of the two spans which the pier under
consideration helps to support.
Second. The impacts given by formula for any span are the greatest
that can come upon any main truss-member thereof, and are much
larger than those for the span as a whole, as indicated by the ratio of mid-span deflections under the same load when moving and when quiescent.
Third. The critical speed which produces the impact given by formula
is likely to be developed very seldom, if at all, on any particular bridge.
Fourth. The massiveness of the pier will absorb some of the shock that
reaches its top before the said shock passes to the base.
Fifth. As the tops of the piles are encased in the mass of concrete, they
will act together as a unit and thus lessen somewhat the impact per pile.
|