TITLE ABOUT CONTENTS INDEX GLOSSARY < PREV NEXT >
 
 
62 ECONOMICS OF BRIDGEWORK Chapter VII

g. Interruptions to travel over the structure from opening the movable

span.

h. A somewhat greater obstruction of the thoroughfare in respect to

vessel traffic as well as to the passage of the water, in case of

the adoption of a swing span with its protection.

 

A thorough consideration of all these criteria will have to be made before a logical conclusion can be reached as to which type of layout is preferable.

The correct ratio of first costs for a low-level bridge and a high-level one of the same capacity and strength at any proposed crossing must, of course, be determined from layouts, computations of quantities of materials, and estimates based upon current prices of the said materials and of labor. It is sometimes necessary, however, to make a hurried economic comparison; and as an aid in so doing the author has established the following results, based upon assumed conditions that may properly be deemed average or normal.

Let us assume a double-track-railway crossing of a river like the Missouri, requiring 1,500 feet of main spans with a vertical clearance of 50-feet above high water for passing vessels, a variation of twenty-five feet between extreme stages of water, a horizontal bed-rock 75 feet below high-water elevation, one bank high and sloping back from high-water line at a ratio of three horizontal to one vertical and the other bank level and very low; and let the approach grades be one per cent. Under such conditions the deepest water will nearly always be found comparatively close to the higher bank, and the position of channel will be permanent; consequently it would be legitimate to employ a single through span over the second opening from the high-bank end.

With certain assumed medium unit prices for materials in place, the minimum costs of these two structures proved to be as follows:

Low-Level Bridge$1,204,000
High-Level Bridge$1,530,000
The ratio of these costs is 1.27

 

With a low, flat approach on each side, and the other conditions unchanged, it would be necessary in the case of the high-level bridge to adopt a level grade over the entire river so as to provide against any drastic shifting of channel; and in the case of the low-level bridge to figure on being able to take down the towers, machinery, and house and shift them to any one of the other openings. Under these conditions the costs of the two structures proved to be as follows:

Low-Level Bridge$1,256,000
High-Level Bridge$2,604,000
The ratio of these costs is 2.08

 

 
TITLE ABOUT CONTENTS INDEX GLOSSARY < PREV NEXT >
 
Lichtenberger Engineering Library - The University of Iowa Libraries
Contact Us
© 2003 The University of Iowa